Oct. Denny/Sealth project update
The Seattle School District Building Excellence III capital program has just released its latest update on the Denny/Sealth campus project.
The full text is below. Click here for past updates on this project.
"As of the end of September, 2009, the new Chief Sealth boilers are complete and awaiting the final report. The installation of the sewer line and water on the north end of the project was completed.
"The old Chief Sealth courtyards have been demolished and the contractor began framing walls and completing mechanical, electrical and plumbing rough-in in Chief Sealth High School.
"The contractor is 80 percent complete with the installation of the footings for the new Galleria and Denny International Middle School and 75 percent complete with the underground utilities for the new Galleria.
"The contractor also began erecting walls for the new middle school gymnasium.